Overnight charging for your vans and company cars
AC fleet charging, sized to your base
Most fleets don't need rapid chargers. Vans and company cars sit at base overnight, so 7kW or 22kW AC charging fills them up for the morning, at a fraction of the cost.
We install 2 to 40 sockets with load management, sharing the power you already have so we can avoid a costly supply upgrade wherever possible.
Fuuse reporting shows the energy used by each vehicle, so you know exactly what every van or car costs to run.
Workplace Charging Scheme
Where eligible, the Workplace Charging Scheme pays up to £500 per socket, for up to 40 sockets. It closes on 31 March 2027. We check eligibility and handle the claim with you.
- Vans and company cars returning to base
- 2 to 40 sockets, 7kW and 22kW
- Load management, no costly supply upgrade where possible
- Fuuse reporting per vehicle
Built for Fleet Operations
Reliable overnight charging designed around your schedules
Overnight Charging
Charge your fleet while vehicles are parked overnight. Full batteries ready for the morning run.
Shift-Friendly
Designed around your working patterns, whether short turnaround shifts for coaches, staggered HGV departures, or standard van fleet schedules.
7kW and 22kW AC
The right power for vans and cars parked overnight. 2 to 40 sockets, matched to your vehicles and mileage. DC rapid options for HGVs and coaches are covered further down.
Per-vehicle reporting
Fuuse reporting shows energy and cost for every vehicle, ready for reimbursement and fleet reports.
Phased Rollout
Install infrastructure now, expand later. Start with a few chargers and scale as your fleet grows.
Power Management
Load balancing ensures your depot doesn't exceed its electrical capacity, even at full charge. DNO-managed connections for larger sites where needed.
Compliance & Safety
OZEV-approved installations with full certification and ongoing compliance support.
Uptime & Support
Proactive maintenance keeps your chargers running. Downtime means lost routes and revenue.
How We Work
Simple, straightforward process from enquiry to install.
Site Survey
We assess your depot layout, parking bays, electrical capacity, and vehicle schedules.
Infrastructure Design
A phased plan that fits your current fleet and future growth, within your power budget.
DNO & Approvals
We handle any Distribution Network Operator notifications and supply upgrade applications.
Installation
Minimal disruption. We work around your operations, weekends and evenings if needed.
Commission & Maintain
Testing, driver training, and optional ongoing maintenance to keep everything running.
Keep Chargers Reliable
Downtime means missed routes. Our maintenance packages keep your depot charging estate running.
View Maintenance & Support →How Depot Charging Is Planned
Depot charging is an energy problem before it is an equipment problem. The number of chargers you need is not the number of vehicles you run, it is whatever delivers the required kilowatt-hours into the fleet between the last vehicle returning at night and the first one leaving in the morning. Get that calculation right and most depots need far less installed power than the vehicle count suggests.
Sizing against the duty cycle
We start with daily mileage per vehicle and realistic miles-per-kWh for the duty being performed, a loaded 3.5t van in winter is a very different figure to a manufacturer's brochure. That gives the nightly energy requirement. Divided across the hours vehicles are actually stationary, it gives the average power draw the site must sustain. A fifteen-van fleet parked from 6pm to 6am rarely needs anything close to fifteen times 7kW.
Load management instead of a supply upgrade
Dynamic load management reads the site's live demand and shares whatever headroom remains between active chargers, sequencing vehicles across the overnight window. It costs a fraction of a Distribution Network Operator supply upgrade and avoids the months-long connection timescale that comes with one. Where an upgrade genuinely is unavoidable, typically eHGV depots and high-power DC installations, we apply to the DNO early and plan the rollout around the energisation date rather than hoping for it.
Civils once, chargers in phases
The expensive parts of a depot install are the trenching, ducting, sub-main and distribution board. Those are shared across every charge point on site, so installing them for the full future estate during the first dig is dramatically cheaper than returning to break the same ground twice. Spare ducting laid at build time costs very little; a second mobilisation, excavation and reinstatement costs a great deal.
Matching charger power to turnaround
Van fleets returning to base for the night are well served by 7kW or 22kW AC units. Coaches, eHGVs and any vehicle with a short mid-shift dwell need DC, typically 50kW to 150kW, and that changes the supply conversation entirely. Mixed fleets often run both, with AC on the overnight bays and a smaller number of DC units for fast turnaround.
Uptime is an operational requirement
A charger that fails overnight is a route that does not run in the morning. We specify OCPP-compliant hardware with remote monitoring so faults surface before the depot manager finds them, agree a response SLA that matches your operational tolerance, and build in enough redundancy that a single unit failure never strands a shift.
Larger depots: HGVs, coaches and DC charging
Multiple vehicles, limited power, tight schedules. Depot charging needs careful planning to work reliably without expensive supply upgrades.
We design load-managed systems that charge your full fleet within your overnight window, using your existing electrical capacity wherever possible.
Start with what you need now. Our phased approach means the infrastructure is ready to expand as more vehicles go electric.
Larger depot charging works for:
- Electric van fleets returning to base
- eHGV operators and logistics hubs
- Coach and bus operators
- Delivery and last-mile fleets
- Council and public sector vehicle depots
- Mixed fleets on phased electrification programmes
Depot Charging Scheme: get ready for Window 2
Window 2 opens 28 October 2026 and closes 29 January 2027, for projects starting from April 2027 and completed by 31 March 2028. Window 1 closed on 30 June 2026. Window 1 funded 70% of chargepoint and civil costs, up to £1 million per organisation. Rates for later windows are expected to reduce, so we confirm the current figure when the window opens.
Eligibility at a glance:
- At least one battery electric van, HGV or coach in your fleet (current or planned)
- UK-registered, operating for at least 1 year
- You own or lease one or more UK depots
- Window 1 funded 70% of eligible costs, up to £1 million per organisation
- One application per organisation, make it count
Applications are assessed first come, first served. We'll advise on eligibility and application support during your site survey. If some vans go home with drivers, see our page on vans that go home with drivers.
Checked September 2026Frequently Asked Questions
Got questions? We've got straight answers.
Plan your depot, and your Window 2 application
Three short steps. An engineer will call you within one working day, or ring us on 0330 6330 375.